Welcome to the Cape Cod Builder blog

Follow the Build with REEF

Posted by REEF Cape Cod's Home Builder on Wed, Aug 22, 2018

Have you ever wanted to see how a custom home is built on Cape Cod from start to finish? REEF and it's team of contractors have been selected for a special project called "Follow the Build" where you can watch one of our current projects from start to finish. The project is a custom home in a FEMA flood zone near Barnstable Harbor which was designed to meet all of the special requirements of flood zone construction and still meet the stringent requirements of the Old King's Highway Historic District. The original home on the property was built in the 1950's and was flooded twice during the winter of 2018, and the decision was made to rebuild.

PART_1515092862783_image000000

Due to the small lot size and busy location near the harbor, the REEF team worked with our suppliers and framing contractors to build most of the project components off site. This minimized the time on the site, and the number of deliveries as the summer traffic near the harbor can be incredibly heavy. We worked with Shepley Wood Products and Cape Cod Panel and TM Framing to pre-fabricate most of the project off site. So what are the results? 1) Incredibly accurate and well made framing, assembled with computer controlled nailing machines, that far exceed the high wind zone structural requirements 2) Dramatic savings and time and waste on the job site, in fact we were able to build the frame of this 2300sf home with porches and decks in about 1 week !

Follow the build project here: Follow the build with REEF!

 

 

If you are considering building a Custom Home on Cape Cod, click here to find out more about Cape Cod Construction Costs

If you have a Waterfront Project in mind, click here to download our Waterfront Property Guide

 

Tags: FEMA flood zones, Cape Cod Builder, waterfront custom home

2018 Construction Cost Guide for Cape Cod

Posted by REEF Cape Cod's Home Builder on Tue, May 01, 2018

The 2018 Construction Cost Guide is here! See how all of the various economic, labor, building code and trade issues will impact your Cape Cod home project.

73RowLR-8

Click Here to download: 2018 Construction Cost Guide

73RowLR-3

Tags: new construction rates per square foot harwich ma, Building Costs, new construction rates per square foot chatham ma, waterfront custom home, provincetown, Construction Costs, cost per square foot

Building a Waterfront Home Part IV

Posted by REEF Cape Cod's Home Builder on Tue, Nov 21, 2017

IMG_20171116_120605

Since the last part of this series a lot has happened! We completed the design process and were able to obtain our final building permits through the town's building department. This process should take about 30 days, but with a large home, expect lots of questions from the building commissioner. Structural details and engineering had to be submitted and reviewed with our engineer and this process takes time. We began work in September, clearing the site and moving out excess soil that would have otherwise been in our way for construction.

IMG_20171006_110952

IMG_20171006_110918

Most of this soil will have to be brought back into the site for back fill, due to the limited area to work and the constraints inherent to construction in a conservation area. With the fill removed, we were able get to work on the basement footings and walls.

Photo Nov 09, 11 45 24 AM (1)

After the footings are installed, the next step is to form and place concrete in the lower level walkout basement walls, which will remain below grade once complete - you can see the form work in the next photo

IMG_20171113_075558

IMG_20171113_075640

Once the concrete has been poured in the lower walls and it has cured, the forms are removed and rigid foam insulation is placed against the walls to protect from frost from migrating through the foundation walls and heaving the soils below the house.

Here are some pictures with the foam insulation installed:

Resized952017111595095020

Resized952017111595094951

With the foam in place - the lower walls can now be back filled and we are ready to grade and compact the soils under the areas inside the footings to prepare for the flood slab. This is an important step in the process, as it saves time because it would be impossible to use heavy equipment inside the foundation after the walls are poured.

IMG_20171116_120605

IMG_20171113_075606

IMG_20171116_120602

Next steps? This week we will be setting up the rest of the form work for the basement, installing the remaining reinforcing bars and pouring concrete in the walls! We will also start working on the foundation waterproofing system, drainage work and the plumbing that will go under the slab for the basement bathrooms.

If you are considering designing and building a waterfront new home, please consider our team here at REEF!

Here are some more useful links!

Construction Cost Guide for Cape Cod

Waterfront Property Guide

Interested in Post and Beam construction - check out our Timberpeg Page

Tags: waterfront custom home, waterfront, beach house, foundations, excavation

Subscribe to Email Updates

Latest Posts